Sunday, April 21, 2019 – Saturday, April 27, 2019: Project Update & Photos

Ongoing installation of drainable aggregate base material for N/B curb lane@ the intersection of Metro Bus Depot Exit. Sta. 139+00.

Installation of plant bed soil in the front of the church on north corner of Minn. Ave/Gault Pl

Placing of drainable aggregate base on nonwoven geotextile for NB curb lane intersection of Metro Bus Depot Exit. Sta. 138+40 – 139+00

The contractor did the following work: Relocated barricades and began full depth roadway excavation and reconstruction of center lane between WMATA/DOES access drive and Gault Pl Continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at intersection with Benning Rd; install street light poles along Minnesota Ave; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, April 14, 2019 – Saturday, April 20, 2019: Project Update & Photos

Ongoing installation of drainable aggregate base material for N/B curb lane@ the intersection of Metro Bus Depot Exit. Sta. 139+00.

Installation of plant bed soil in the front of the church on north corner of Minn. Ave/Gault Pl

Placing of drainable aggregate base on nonwoven geotextile for NB curb lane intersection of Metro Bus Depot Exit. Sta. 138+40 – 139+00

The contractor did the following work: Continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at intersection with Benning Rd; install street light poles along Minnesota Ave; continued full depth roadway excavation and reconstruction of northbound curb lane between WMATA/DOES access drive and Gault Pl; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, April 7, 2019 – Saturday, April 13, 2019: Project Update & Photos

Ongoing installation of drainable aggregate base material for N/B curb lane@ the intersection of Metro Bus Depot Exit. Sta. 139+00.

Installation of plant bed soil in the front of the church on north corner of Minn. Ave/Gault Pl

Placing of drainable aggregate base on nonwoven geotextile for NB curb lane intersection of Metro Bus Depot Exit. Sta. 138+40 – 139+00

The contractor did the following work: Continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at intersection with Gault Pl; install street light poles along Minnesota Ave; continued full depth roadway excavation and reconstruction of northbound curb lane between WMATA/DOES access drive and Gault Pl; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, March 31, 2019 – Saturday, April 6, 2019: Project Update & Photos

Ongoing work Minnesota Ave/Grant Street.

Ongoing work on roadway subbase in front of school.

Ongoing subbase work.

The contractor did the following work: Continued installation of rebar for retaining wall on the SW corner of Minnesota Ave/Benning Rd intersection; continued full depth roadway excavation and reconstruction of northbound curb lane between WMATA/DOES access drive and Gault Pl; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.