December 2018

Sunday, December 23, 2018 – Saturday, December 29, 2018: Project Update & Photos

Ongoing permeable paver work on the east side of Minnesota Ave.

Temporary restoration of area where existing curb was removed between Sta. 125+00 – 125+75.

Ongoing removal of existing curb.

The contractor did the following work: Placed sand based structural soil and concrete edge restraints for sidewalk on the east side of Minnesota Ave and planter box in front of 4041 Minnesota Ave.; installed concrete edge restraint; stone base, pervious concrete sidewalk and concrete cap for brick wall in front of Friendship Academic Collegiate School on Minnesota; installed underdrain pipe for brick wall in front of Friendship Academic Collegiate School; placed sand base structural soil for sidewalk planter box in front of 4065 Minnesota Ave; installed permeable concrete pavers on the east side of Minnesota Ave between; demolished and removed existing granite curb; installed brick pavers for east side sidewalk in front of Auto Zone; replaced damaged concrete bus pad on east side of Minnesota Ave, north of Benning Rd.

Sunday, December 16, 2018 – Saturday, December 22, 2018: Project Update & Photos

Installation of precast concrete cap for brick wall in the front of Friendship Collegiate Academy School.

Ongoing excavation of sidewalk east side of Minnesota Ave.

Ongoing sidewalk excavation.

The contractor did the following work: Continued work on LID structures at intersection with Grant St; excavated and placed sand base structural soil for planter box and placed concrete for concrete edge restraint in front of Yellow House Restaurant/Metro PCS store and Health Service center building on Minnesota Ave; excavated for street light pole foundations between Grant St. and Gault Pl; excavated for traffic signal foundation on NE corner of Grant St. excavation and installation for traffic signal and street light pole foundations; installed street light pole LED fixtures in front of Park 7 building and light pole in front of Shark Plaza on Minnesota Ave; continued with excavating & installing of sand base structural soil for planter box in front of Shark Plaza continued working on the relocation of the twelve- inch gas main on the west side of Minnesota Ave.

Sunday, December 9, 2018 – Saturday, December 15, 2018: Project Update & Photos

Installation of brick for additional storm drain manhole MH-31A at Minnesota Ave station 138+25 to drain runoff from Collegiate College.

Concrete and steel plate placement for utility duct bank for traffic signal between Minnesota Ave sta. 138+50 to 139+50.

Compaction of 10” aggregate base for south bound lanes of Minnesota Ave between sta. 129+25 to130+25.

The contractor did the following work: Continued work on LID structures at intersection with Grant St; excavated and placed sand base structural soil for planter box and placed concrete for concrete edge restraint in front of Yellow House Restaurant/Metro PCS store and Health Service center building on Minnesota Ave; excavated for street light pole foundations between Grant St. and Gault Pl; excavated for traffic signal foundation on NE corner of Grant St. excavation and installation for traffic signal and street light pole foundations; installed street light pole LED fixtures in front of Park 7 building and light pole in front of Shark Plaza on Minnesota Ave; continued with excavating & installing of sand base structural soil for planter box in front of Shark Plaza continued working on the relocation of the twelve- inch gas main on the west side of Minnesota Ave.

Sunday, December 2, 2018 – Saturday, December 8, 2018: Project Update & Photos

Installation of streetlight in front of Park 7 building.

Ongoing sand base structural soil backfill for planter box on the east side of Minnesota Ave between Sta.138+10 – 138-80.

Ongoing excavation & placing of sand based structural soil.

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; placed permeable concrete sidewalk along the west side of Minnesota Ave; continued excavating and installing of underdrain and granite curb in front of DOES building; continued working on LID structures between DOES access driveway and Metro Station exit drive; excavation and installation for traffic signal and street light pole foundations; placed concrete for traffic signal poles at the corner of Minnesota Ave and Metro Parking garage at Minnesota Ave station Placed concrete for wheelchair/Bicycle Ramps at the SW corner of DOES garage entrance/Minnesota Ave; Install form work for planter boxes along the west sidewalk area.