Sunday, December 16, 2019 – Saturday, December 21, 2019: Project Update & Photos

Ongoing roadway work of N/B curb lane Minnesota Ave.

Basin cabin I-131 connecting pipe installation.

Work on I-131.

The contractor did the following work: Continued with the excavation of existing northbound curb lane pavement in front of Crown gas station continued planting shrubs & ground covers and mulching at NW corner of Minnesota Ave/Benning Rd intersection, in front of 7-Eleven, Yum’s Carryout,Rainbow store, and between building #3919; continued installing bike racks, park benches, and trash cans on Benning Rd; installed permeable concrete paver on the east side of Minnesota Ave from Nannie Helen Burroughs Ave toward Sheriff Rd; began excavating and installing fire hydrant on the west side of Minnesota Ave north of Nannie Helen Burroughs Ave intersection.

Sunday, December 8, 2019 – Saturday, December 14, 2019: Project Update & Photos

Ongoing roadway work on the northbound curb lane north of Nannie Helen Burroughs Ave intersection.

Placing concrete around installed basin connecting pipe at I-127.

Placing of drainable asphalt.

The contractor did the following work: Continued with the excavation of existing northbound curb lane pavement in front of Crown gas station continued planting shrubs & ground covers and mulching at NW corner of Minnesota Ave/Benning Rd intersection, in front of 7-Eleven, Yum’s Carryout,Rainbow store, and between building #3919; continued installing bike racks, park benches, and trash cans on Benning Rd; installed permeable concrete paver on the east side of Minnesota Ave from Nannie Helen Burroughs Ave toward Sheriff Rd; began excavating and installing fire hydrant on the west side of Minnesota Ave north of Nannie Helen Burroughs Ave intersection.

Sunday, December 2, 2019 – Saturday, December 7, 2019: Project Update & Photos

Minnesota Ave facing south on Watts Branch bridge.

Resetting of jersey barrier for full depth northbound curb lane excavation between Crown gas station and Auto Clinic.

Ongoing pavement marking at Minnesota Ave/Hayes Pl.

The contractor did the following work: Excavated and installed granite curb from Nannie Helen Burroughs Ave toward Sherriff Rd on the west side of Minnesota Ave; installed plants in front of7‐Eleven; painted thermoplastic crosswalk at WMATA Bus Depot Exit and at the junction of Minnesota Ave/Grant St; painted thermoplastic cross walk marking at intersection of Minnesota Ave/Gault Pl and Minnesota Ave/Hayes St.; began install catch basin connecting pipe; continue installing traffic light signal at the intersection of Minnesota Ave/Benning Rd.