Sunday, February 24, 2019 – Saturday, March 2, 2019 : Project Update & Photos

Ongoing work on Bioretention structure BIO‐15 on the west side of Minnesota Ave. (Minnesota Metro Station).

Building of formwork for Bio‐14 front wall on west side of Minnesota Ave between Sta. 143+67 ‐ 144+46..

Continued removing tree at the SW corner of Nannie Helen Burroughs Ave/Minnesota Ave intersection.

The contractor did the following work: Continued excavation and footing installation for retaining wall on the NW corner of Minnesota Ave/Nannie Helen Burroughs intersection; installed street light poles on both sides of Minnesota Ave between 4077 Minn. Ave and Metro Bus Depot Exit; completed sidewalk demolition on the west side of Minnesota Ave from the Metro Bus Depot Exit to the Entrance and placed aggregate base for sidewalk and edge restraint; installed trench drain at Sharks Plaza; continued Washington Gas line relocation along  Minnesota Ave.

Sunday, February 17, 2019 – Saturday, February 23, 2019 : Project Update & Photos

Ongoing work on bioretention BIO-14 on the west side of Minnesota Ave in front of Metro Station.

Ongoing fence reinstallation.

Reinstallation of fence at the Metro Bus Depot.

The contractor did the following work: clearing and grubbing for retaining wall on the NW corner of Minnesota Ave/Nannie Helen Burroughs intersection; Excavated and placed concrete for street light pole foundations and traffic signal pole foundations at the Metro Bus Depot; installed electrical conduit from electrical manhole to street light pole foundations; installed granite curb & PCC gutter on the west side of Minnesota Ave (in front of the Metro Bus Depot); installed trench drain concrete at Auto Zone parking lot and excavated for trench drain at Sharks Plaza parking lot; installed concrete wheelchair ramps at Metro Bus Depot on west side of Minnesota Ave; continued Washington Gas line relocation along  Minnesota Ave.

Sunday, February 3, 2019 – Saturday, February 9, 2019 : Project Update & Photos

 

The contractor did the following work: Placed aggregate base asphalt on excavated roadway sub-grade between Benning Rd intersection and Auto Zone; excavated sidewalk and installed pervious concrete sidewalk, brick pavers, bio-retention walls, and capstone for brick wall, installed storm water PCC pipe and soil for planters; continued Washington Gas line relocation along Minnesota Ave between Hayes St and Hunt Pl.