Sunday, May 26, 2019 – Saturday, June 1, 2019: Project Update & Photos

Ongoing work Gault Pl to Hunt Pl NB curb lane Minnesota Ave.

New asphalt base for roadway pavement N/B curb lane from Gault Pl to Hayes St.

Asphalt and new driveway work in front of the WMATA Bus Depot Exit.

The contractor did the following work: Started full depth roadway excavation and reconstruction of northbound curb lane between Gault Pl and Hayes St; continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on northbound Minnesota Ave between Hayes St and Hunt Pl; continued trench excavation for storm water main at the intersection of Minnesota Ave/Nannie Helen Burroughs Ave ; Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, May 19, 2019 – Saturday, May 25, 2019: Project Update & Photos

Base asphalt for northbound curb lane roadway section on Minnesota Ave between Sta. 143+00 – 145+50.

Installation of granite curb and gutter in the front of Big D store and Flower shop Sta. 150+75 to 151+75.

Asphalt base work.

The contractor did the following work: Removed Jersey barriers from south bound curb lane and reopened area in the front of WMATA Bus Depot to traffic; placed Jersey barriers and began full depth roadway excavation and reconstruction of northbound curb lane between Grant St and Gault Pl; continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on northbound Minnesota Ave between Grant St and Gault Pl; continued trench excavation for storm water main at the intersection of Minnesota Ave/Nannie Helen Burroughs Ave ; Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, May 12, 2019 – Saturday, May 18, 2019: Project Update & Photos

Ongoing concrete & asphalt work at the Bus Depot entrance Minnesota Ave (Sta. 142+25 to 143+25).

Installed HMA base asphalt southbound curb lane of Minn. Ave & Gault Pl to WMATA Bus Depot entrance Sta. 143+25 – 145+00.

Installation of 8” ductile iron pipe for water line at Hayes St Sta. 48+40 (K21‐ST0+42).

The contractor did the following work: Removed jersey barrier from the southbound curb lane of Minnesota Ave; continued full depth roadway excavation and reconstruction of southbound curb lane between WMATA/DOES access drive and Gault Pl; excavated and installed WMATA Bus Depot Entrance concrete driveway apron; continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at intersection with Benning Rd; Excavated and installed utility manhole in the front of Exxon gas station; Began trench excavation for storm water main at the intersection of Minnesota Ave/Nannie Helen Burroughs Ave ; Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, May 5, 2019 – Saturday, May 11, 2019: Project Update & Photos

Base asphalt for south bound curb lane roadway section on Minnesota Ave between Sta. 139+25 – 142+25.

Ongoing concrete driveway and base asphalt work on Minnesota Ave between Sta. 141‐34 – 142+10.

Ongoing road pavement work in the front of WMATA Bus Depot entrance (Sta. 141+25 – 142+25).

The contractor did the following work: Shifted southbound traffic to the newly placed median lane of Minnesota Ave; continued full depth roadway excavation and reconstruction of southbound curb lane between WMATA/DOES access drive and Gault Pl; continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at Hayes Street; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.

Sunday, April 28, 2019 – Saturday, May 4, 2019

Prepared subbase ready for base asphalt.

Completed roadway median lane on Minnesota Ave between Sta. 138+40 – 139+55.

Base asphalt work roadway median lane in front of WMATA station Exit on Minnesota Ave (Sta. 138+40 – 139+55).

The contractor did the following work: Relocated barricades and began full depth roadway excavation and reconstruction of center lane between WMATA/DOES access drive and Gault Pl; continued installation of curb and gutter, pervious concrete sidewalks, handicap ramps and brick pavers on Minnesota Ave at intersection with Benning Rd; install street light poles along Minnesota Ave; continued Washington Gas line relocation along Minnesota Ave at Benning Rd and between Hunt Pl and Hayes St.