November 2018

Sunday, November 25, 2018 – Saturday, December 01, 2018: Project Update & Photos

Newly placed asphalt road base for south bound lanes of Minnesota Ave between sta. 133+75 to 138+50 (in front of DOES building).

Placing of 2nd lift of hot mix asphlat BM-25.0M for south bound lanes of Minnesota Ave between stations 133+75 to 138+50.

Restoration of trench cut on Minnesota Ave (east side) NE.

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; placed permeable concrete sidewalk along the west side of Minnesota Ave; continued excavating and installing of underdrain and granite curb in front of DOES building; continued working on LID structures between DOES access driveway and Metro Station exit drive; excavation and installation for traffic signal and street light pole foundations; placed concrete for traffic signal poles at the corner of Minnesota Ave and Metro Parking garage at Minnesota Ave station Placed concrete for wheelchair/Bicycle Ramps at the SW corner of DOES garage entrance/Minnesota Ave; Install form work for planter boxes along the west sidewalk areaof Minnesota Ave; pot hole repair in north bound lanes of Minnesota Ave; Installed 15” catch basinconnecting pipe and concrete cradle from existing manhole MH-42 to catch basin on Minnesota Av /Hayes St intersection; placed hot mix asphalt patch over excavated trenches for water service connection between Hunt Pl and Hayes St along Minnesota Ave.

Sunday, November 18, 2018 – Saturday, November 24, 2018: Project Update & Photos

Newly placed asphalt road base for south bound lanes of Minnesota Ave between sta. 133+75 to 138+50 (in front of DOES building).

Placing of 2nd lift of hot mix asphlat BM-25.0M for south bound lanes of Minnesota Ave between stations 133+75 to 138+50.

Restoration of trench cut on Minnesota Ave (east side) NE.

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; excavated and re-graded sections of the west sidewalk of Minnesota Ave for repair; excavated and installed 6” under drain pipe for sidewalk curb on west; placed permeable concrete sidewalk for sidewalk along the west side of Minnesota Ave Continued excavating and installing of under drain and granite curb in front of DOES building; continued working on LID structures between DOES access driveway and Metro Station exit drive; excavation and installation for traffic signal and street light pole foundations; placed concrete for traffic signal poles at the corner of Minnesota Ave and Metro Parking garage at Minnesota Ave station Placed concrete for wheelchair/Bicycle Ramps at the SW corner of DOES garage entrance/Minnesota Ave; Install form work for planter boxes along the west sidewalk area of Minnesota Ave; pot hole repair in north bound lanes of Minnesota Ave; Installed 15” catch basin connecting pipe and concrete cradle from existing manhole MH-42 to catch basin on Minnesota Av /Hayes St intersection; placed hot mix asphalt patch over excavated trenches for water service connection between Hunt Pl and Hayes St along Minnesota Ave.

Sunday, November 11, 2018 – Saturday, November 17, 2018: Project Update & Photos

Demolition of exsiting roadway surface for full depth excavation for south bound lanes of Minnestoa Ave between stations 134+00 to 136+25.

Installed sand base structural soil for west sidewalk of Minnesota Ave between stations 136+50 to 138+50

Installed sand base structural soil for west sidewalk of Minnesota Ave between sta. 136+00 to 138+50

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; excavated and re-graded sections of the west sidewalk of Minnesota Ave for repair; excavated and installed 6” under drain pipe for sidewalk curb on west; placed permeable concrete sidewalk for sidewalk along the west side of Minnesota Ave Continued excavating and installing of under drain and granite curb in front of DOES building; continued working on LID structures between DOES access driveway and Metro Station exit drive; excavation and installation for traffic signal and street light pole foundations; placed concrete for traffic signal poles at the corner of Minnesota Ave and Metro Parking garage at Minnesota Ave station Placed concrete for wheelchair/Bicycle Ramps at the SW corner of DOES garage entrance/Minnesota Ave; Install form work for planter boxes along the west sidewalk area of Minnesota Ave; pot hole repair in north bound lanes of Minnesota Ave.

Sunday, November 4, 2018 – Saturday, November 10, 2018: Project Update & Photos

Installation of brick for additional storm drain manhole MH-31A at Minnesota Ave station 138+25 to drain runoff from Collegiate College.

Concrete and steel plate placement for utility duct bank for traffic signal between Minnesota Ave sta. 138+50 to 139+50.

Compaction of 10” aggregate base for south bound lanes of Minnesota Ave between sta. 129+25 to130+25.

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; continued excavating & placing Continued excavating and installing of under drain and granite curb in front of DOES building; continued working on LID structures between DOES access driveway and Metro Station exit drive; Excavation and installation for traffic signal and street light pole foundations; excavated for additional manhole (for Collegiate College runoff which was draining into an unconnected catch basin); excavated for utility conduit duct bank for traffic signals at the intersection of the Metro Bus Depot Exit; placed concrete for traffic signal poles at the corner of Minnesota Ave and Metro Parking garage at Minnesota Ave station Placed concrete for wheelchair/Bicycle Ramps at the SW corner of DOES garage entrance/Minnesota Ave; installed roadway pavement markings for Phase 2A along Minnesota Ave.