Sunday, November 25, 2019 – Saturday, November 30, 2019: Project Update & Photos

Ongoing tree planting.

Intersection of Nannie Helen Burroughs Ave/Minnesota Ave.

Excavating around catch basin I‐128.

The contractor did the following work: Installed pervious concrete sidewalk between Nannie Helen Burroughs Ave and Sheriff Rd on the east side of Minnesota Ave; placed #57 aggregate material for pervious concrete sidewalk base between Nannie Helen Burroughs Ave and Sheriff Rd on the east side of Minnesota Ave; full depth excavation and paving of Minnesota Ave/Nannie Helen Burroughs Ave intersection; Excavated existing curb, gutter, and wheelchair ramp at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection; continued pulling electrical cables, began installing traffic signal light at WMATA Bus Depot Exit; continued pulling traffic signal cables; excavated existing sidewalkcontinued cleaning planter boxes and adding more planter soil; continued planting trees along Minnesota Ave between Benning Rd and WMATA/DOES parking garage alley entrance

Sunday, November 18, 2019 – Saturday, November 23, 2019: Project Update & Photos

Minnesota Ave facing north from Hunts Pl.

Ongoing planter edge work at NE corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection.

Ongoing trench excavation from I‐128 to new manhole near ‐132.

The contractor did the following work: Installed pervious concrete sidewalk between Nannie Helen Burroughs Ave and Sheriff Rd on the east side of Minnesota Ave; placed #57 aggregate material for pervious concrete sidewalk base between Nannie Helen Burroughs Ave and Sheriff Rd on the east side of Minnesota Ave; full depth excavation and paving of Minnesota Ave/Nannie Helen Burroughs Ave intersection; Excavated existing curb, gutter, and wheelchair ramp at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection; continued pulling electrical cables, began installing traffic signal light at WMATA Bus Depot Exit; continued pulling traffic signal cables; excavated existing sidewalkcontinued cleaning planter boxes and adding more planter soil; continued planting trees along Minnesota Ave between Benning Rd and WMATA/DOES parking garage alley entrance

Sunday, November 11, 2019 – Saturday, November 16, 2019: Project Update & Photos

Ongoing base asphalt pavement at Minnesota Ave/Nannie Helen Burroughs Ave intersection.

Preparation for pervious concrete side walk on west of Minnesota Ave.

Ongoing surface asphalt work on Minnesota Ave.

The contractor did the following work: full depth excavation and paving of Minnesota Ave/Nannie Helen Burroughs Ave intersection; Excavated existing curb, gutter, and wheelchair ramp at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection; continued pulling electrical cables, began installing traffic signal light at WMATA Bus Depot Exit; continued pulling traffic signal cables; excavated existing sidewalk, built formwork and placed concrete for sidewalk on east side of Minnesota Ave between Sheriff Rd to northern driveway of Auto Clinic shop; continued with ornamental tree fence installation.

Sunday, November 4, 2019 – Saturday, November 9, 2019: Project Update & Photos

Ongoing placement of base asphalt work @ Nannie Helen Burroughs Ave/Minnesota Ave intersection.

Ongoing base asphalt pavement at Minnesota Ave/Nannie Helen Burroughs Ave intersection.

Ongoing work on southern Auto Clinic shop entrance driveway on the east side of Minnesota Ave.

The contractor did the following work: Setup MOT and reset jersey barriers for full depth excavation of northbound curb lane roadway pavement between Sheriff Rd to Auto Doctor shop; Excavated existing curb, gutter, and wheelchair ramp at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection; placed concrete sidewalk in uncompleted sections at Hayes St and Hunt Pl; continued pulling electrical cables, installed street light arm and light fixture at the intersection of Minnesota Ave/Benning Rd; continued pulling traffic signal cables at the intersection of Minnesota Ave/Benning Rd; continued with ornamental tree fence installation.

Sunday, October 28, 2019 – Saturday, November 2, 2019: Project Update & Photos

Ongoing placement of GAB work @ Nannie Helen Burroughs Ave/Minnesota Ave intersection.

Ongoing base asphalt pavement at Minnesota Ave/Nannie Helen Burroughs Ave intersection.

Ongoing pavement work medina roadway Minnesota Ave.

The contractor did the following work: Continued with full depth excavation from Sherriff Rd, NE to Nannie Helen Burroughs Ave; backfilled excavated trench for duct bank at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave; Continued installing permeable concrete pavers on the west side of Minnesota Ave between WMATA “Park, Kiss “N” Ride” lot entrance &Watts Branch bridge; continued with ornamental tree fence installation; continued with ornamental tree fence installation.