Sunday, October 21, 2019 – Saturday, October 26, 2019: Project Update & Photos

Asphalt base work @ Nannie Helen Burroughs Ave/Minnesota Ave intersection.

Minnesota Ave/Nannie Helen Burroughs Ave intersection.

Ongoing pavement work west bound curb lane Nannie Helen Burroughs Ave.

The contractor did the following work: Continued with full depth excavation from Sherriff Rd, NE to Nannie Helen Burroughs Ave; placed concrete for half of the Fire Station No. 27 driveway, gutter, wheelchair ramp on the east side of Minnesota Ave; Excavated existing sidewalk at the SE corner of Minnesota Ave/Hunt Pl junction; Began excavating for catch basin connecting pipe from I‐129 to existingmanhole at the NW corner of Minnesota Ave/Nannie Helen Burroughs Ave intersection; Backfilled excavated trench for duct bank at SE corner of Minnesota Ave/Nannie Helen Burroughs Ave; Continued installing permeable concrete paver on the west side of Minnesota Ave between WMATA “Park, Kiss “N” Ride” lot entrance &Watts Branch bridge; Removed existing traffic signal pole and reset on temporary base at the median island west side of Minnesota Ave/Nannie Burroughs Ave intersection; continued with ornamental tree fence installation.

Sunday, October 14, 2019 – Saturday, October 19, 2019: Project Update & Photos

Ongoing asphalt base work.

Ongoing paving work.

Concrete bus pad work on Minnesota Ave north bound lane north of Nannie Helen Burroughs Ave intersection.

The contractor did the following work: Continued with full depth excavation in the median lane from Watts Branch bridge to Nannie Helen Burroughs Ave; Placed asphalt base; continued building edge restraint and placing #57 aggregate material base for pervious concrete sidewalk on the east side of Minnesota Ave; Placed pervious concrete sidewalk on the east side of Minnesota Ave; Excavated and installed electrical conduit from Watts Branch bridge to Nannie Helen Burroughs Ave; Continued with ornamental tree fence installation.

Sunday, October 7, 2019 – Saturday, October 12, 2019: Project Update & Photos

Finished road pavement section Minnesota Ave heading towards Gault Pl junction.

Ongoing paving median lanes Minnesota Ave from Nannie Helen Burroughs Ave to Watts Branch bridge.

Ongoing compaction test.

The contractor did the following work: Continued with full depth excavation from Watts Branch bridge to Nannie Helen Burroughs Ave; Placed asphalt base in the south bound curb lane from Watts Branch Bridge to Nannie Helen Burroughs Ave; Started demolition of north bound curb lane pavement from Hunt Pl to the northern driveway of Exxon gas station ; continued building edge restraint and placing #57 aggregate material base for pervious concrete sidewalk on the east side of Minnesota Ave Continued placing surface asphalt in the north bound curb lane of Minnesota Ave from WMATA Bus Depot Exit to Grant St; WMATA/DOES parking access roadway, south bound curb lane between south end of DOES building to Benning Rd, and installed temporary lane marking; Placed pervious concrete sidewalk on the east side of Minnesota Ave from the Flower shop to Hunt Pl Excavated and installed electrical conduit and formed traffic signal foundation on the south side of Fire Station No. 27; continued with ornamental tree fence installation.

Sunday, September 30, 2019 – Saturday, October 5, 2019: Project Update & Photos

Roadway Minnesota Ave. from Gault Pl toward Hunts Pl.

Ongoing installation of granite curb toward Nannie Helen Burroughs Ave on westside of Minnesota Ave.

Preparation for pervious concrete sidewalk toward Watts Branch bridge on the west side of Minnesota Ave.

The contractor did the following work: The contractor did the following work: Continued with full depth excavation from Watts Branch bridge to Nannie Helen Burroughs Ave, placed geotextile fabric on subgrade & drainable aggregate base asphalt for the north bound curb lane roadway pavement from Hunt Pl to Watts Branch Bridge