TWO-WEEK LOOK AHEAD

12/17/2018 – 12/30/2018

  • Install bio retention in front of Friendship Collegiate School
  • Excavate and install sidewalk in front of Friendship Collegiate School
  • Excavate sidewalk on east side of Minnesota Avenue between Benning Road and Metrobus exit
  • driveway
  • Install street light poles between Benning Road and DOES building
  • Install traffic signal poles at DOES / WMATA Access drive
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5

12/10/2018 – 12/23/2018

  • Excavate and install bio retention in front of Friendship Collegiate School
  • Excavate sidewalk on east side of Minnesota Avenue between Benning Road and Metrobus exit
  • driveway
  • Install street light poles between Benning Road and DOES building
  • Install traffic signal poles at DOES / WMATA Access drive
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5

12/3/2018 – 12/16/2018

  •  Shift traffic to the west side of Minnesota Avenue between Benning Road and Metro bus exit driveway
  • Install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers in front of DOES building
  • Excavate sidewalk on east side of Minnesota Avenue across between Benning Road and Metro bus exit driveway
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • Install electrical duct bank at METRO entrance and exit
  • Excavate, install and connect catch basin between Hayes St, NE and Hunt Pl, NE

11/26/2018 – 12/9/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers in front of DOES building
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • Install electrical duct bank at Metro bus entrance and exit driveways
  •  Shift traffic to the west side of Minnesota Avenue between Benning Road and Metrobus exit driveway
  • Excavate, install and connect catch basin between Hayes St, NE and Hunt Pl, NE

11/19/2018 – 12/2/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers in front of DOES building
  • Install new storm water structures at Metro bus exit drive
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • Install electrical duct bank at Metro bus entrance and exit
  • Excavate, install and connect catch basin between Hayes St, NE and Hunt Pl, NE

11/12/2018 – 11/25/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers in front of DOES building
  • Excavate and install pervious concrete sidewalk in front of Park 7 building
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • Install electrical duct bank at METRO entrance and exit
  • Excavate, install and connect catch basin between Hayes St, NE and Hunt Pl, NE

11/5/2018 – 11/18/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers in front of DOES building
  • Excavate and install pervious concrete sidewalk in front of Park 7 building
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • Install electrical duct bank at METRO entrance and exit
  • Excavate, install and connect catch basin between Hayes St, NE and Hunt Pl, NE

10/29/2018 – 11/11/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers
  • Install curb and gutter on west side of Minnesota Avenue
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • House water connection east side of Minnesota Ave
  • Catch basin connection

10/29/2018 – 11/11/2018

  • Excavate planters, install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers
  • Install curb and gutter on west side of Minnesota Avenue
  • Continue electrical PVC Conduit duct bank work Phases 2, 4, and 5
  • House water connection east side of Minnesota Ave
  • Catch basin connection

10/7/2018 – 10/14/2018

  • Install under drain pipe, stone and geo fabric, water proofing, planter material and structural soil
  • Install asphalt base at right southbound lane of Minnesota Ave north of Benning Road
  • Install curb and gutter on west side of Minnesota Ave
  • Continue electrical PVC Conduit duct bank work Phase 2, 4, and 5
  • House water connection east side of Minnesota Ave northbound
  • Catch basin connection

9/23/2018 – 10/6/2018

  • Install under drain pipe, stone and geo fabric, water proofing, planter material and structural soil
  • Install asphalt base at right southbound lane of Minnesota Ave north of Benning Rd
  • Install curb and gutter on west side of Minnesota Ave
  • Continue electrical PVC Conduit duct bank work Phase 2,4,5
  • House water connection east side of Minnesota Ave northbound
  • Catch basin connection